CCD 171: Pool and Spa Water Treatment Products Review Process
Current Status
Project Milestones
- Project Initiation: June 22, 2009
- EcoLogo conducting background research and populating stakeholder list
- Discussion Document: August 13, 2009
- Stakeholder comments requested regarding proposed scope and direction of standard
- Development of Draft Standard: Final stakeholder comment period took place during March, 2010.
- EcoLogo considers stakeholder feedback on discussion document in development of first draft
- Stakeholder comment period is held for feedback on first draft of standard
- Official Standard Released
- EcoLogo published CCD-171 on May 18, 2010.
Advisory Committee
- EcoLogo has not commissioned an external advisory committee to assist in the development of this standard.
Archive of Documents
Additional Details
- More information on the EcoLogo standard development and review process itself is available here